A 35 kV oil-immersed transformer connects utility, industrial and renewable-energy systems across a wide range of capacities. Because each project has different network and site conditions, the factory design should not start from voltage and kVA alone.
Clear technical data at the beginning reduces drawing revisions, protection changes and civil rework. The purchase specification should identify the guaranteed performance and the physical interfaces the supplier must meet.
Electrical Data That Drives the Design
Confirm rated power, frequency, primary and secondary voltage, highest system voltage, insulation level, vector group, neutral arrangement and tap range. The network study should provide the required impedance and short-circuit withstand duty.
Loss evaluation should distinguish no-load loss, load loss, auxiliary consumption and the economic value assigned to each. A low purchase price may not be the lowest lifecycle cost when the transformer is energized continuously.
Mechanical and Accessory Checklist
Define ONAN or ONAF cooling duty, temperature-rise limits and fan-control stages.
Confirm bushing type, terminal orientation, cable boxes or bus connections and phase spacing.
Specify conservator or sealed-tank arrangement, oil-preservation system and pressure protection.
List gauges, alarms, contacts, marshalling cabinet, CTs and online monitoring points.
Provide transport limits, lifting and jacking points, total mass and shipping configuration.
Coordinate foundation loads, oil containment, fire separation, earthing and maintenance clearances.
Approve Documents Before Materials Are Committed
The review package should include a general arrangement, nameplate data, terminal plan, control schematic, accessory list, foundation loads and guaranteed-loss schedule. Comments must be resolved consistently across electrical and civil drawings.
Factory test scope, witness points, report format and spare parts should be agreed before production. This keeps the final inspection focused on requirements that were defined, priced and engineered from the start.
Прежде чем определять технические требования для вашего проекта, сравните сухие и масляные трансформаторы по таким критериям, как система охлаждения, монтаж, техническое обслуживание, пожарная безопасность, эффективность и сфера применения.
Модернизация подстанции общего назначения требует не только увеличения мощности трансформатора. Оборудование также должно обеспечивать стабильное преобразование напряжения, предсказуемое техническое обслуживание и безопасную интеграцию с существующими системами защиты. В данном примере применения описывается...
Китайский альянс по зарядке электромобилей опубликовал отчет о состоянии работы национальной инфраструктуры зарядки и замены аккумуляторов электромобилей за апрель 2023 года. В апреле 2023 года количество общественных зарядных станций увеличилось на 67 000 по сравнению с мартом, а рост по сравнению с аналогичным периодом прошлого года составил...
Данные, опубликованные Министерством промышленности и информационных технологий, показали, что в 2022 году объемы производства на всех этапах цепочки производства фотоэлектрической продукции достигли рекордного уровня. Объемы производства поликремния, кремниевых пластин, фотоэлементов и модулей в Китае достигли...
Отправить запрос о продукте
Мы свяжемся с вами в течение 24 часов